M1 communications office



In brief

Duration: 2 phases
Installation : Feb. 06 – Aug. 08
Maintenance : Feb. 06 – Dec. 08

Customer:
Balfour Beatty / Skanska jv

Client:
Highways Agency

Value:
£1.44m
Specification

The prime scope of the project was to design and build the complete temporary CCTV system, including a control room console consisting of 3 tiers and 13 bays, ergonomically designed for operator comfort.

The control room itself is air conditioned with an independent power supply and generator back-up.

The annex to the main room houses the multiplexers and DVD storage, the recorded footage is stored for 28 days.


The DW solution


Benefits to client